L1 Studios
images/nr1.jpg

CAPITAL DEVELOPMENTS - Liverpool Property Development

Monday, 20 March 2017 08:39

L1 Studios

L1 Studios – February 2017


Development Progress

L1 Studios was launched in September and is now sold out.

Construction began in April 2017 and is on schedule for completion in Q2, 2018.

Consisting of 52 studio apartments the development will offer luxury student living to supply the growing demand for student accommodation in Liverpool. Investors benefit from receiving 8% net rental income for the first 3 years.

The main progress onsite this month has centred around the excavation of the pile-cap style foundations, which is now complete. The piled foundations have been cropped and the excavations blinded and filled.

 

L1 Studios – Construction Updates

L1 Studios Construction Update - March 2019

L1 Studios Construction Update - February 2019

L1 Studios Construction Update - December 2018

L1 Studios Construction Update - November 2018

L1 Studios Construction Update - October 2018

L1 Studios Construction Update – September 2018

L1 Studios Construction Update – August 2018

L1 Studios Construction Update – July 2018

L1 Studios Construction Update – June 2018

L1 Studios Construction Update – May 2018

L1 Studios Construction Update – April 2018

L1 Studios Construction Update – March 2018

L1 Studios Construction Update – February 2018

L1 Studios Construction Update – December 2017

L1 Studios Construction Update – November 2017

L1 Studios Construction Update – October 2017

L1 Studios Construction Update – September 2017

L1 Studios Construction Update – July 2017

 

L1 Studios – Construction Update May 2017

Following on from previous site investigations and foundation design, May has seen installation of site infrastructure and boarding, and initial groundworks have taken place.

The existing basement that was present from the previous building has been excavated, as have the substructure pilings and foundations. The construction team will commence piling of the new foundations in June, in anticipation of the erection of the steel frame following on from that.

 


L1 Studios – Construction Update February 2017

The developer’s team has recently carried out a site investigation to the plot, which related to environmental searches and to assess the ground for foundation design.

Following this successful investigation, the developer has sent a team onsite to confirm the findings of the site investigation report. The onsite team has also determined the extent of the basement to the adjacent property. These trial site investigations have meant that SWF Consultants are able to finalise the foundation design for the project.

Furthermore, last week saw a design team meeting held, which was attended by the architects for the development, the structural engineer, the M & E engineers and the main contractor, Ridgemere. The purpose of the meeting was to co-ordinate all of the different elements of the building design, which are now being drawn up ahead of full construction commencing onsite in May.

Photographs from Fleet St showing trial / exploratory excavations.

 

L1 Studios Drone Footage – February 2018

Published in Capital
Monday, 20 March 2017 08:33

City Residence - Completed and Tenanted

City Residence – Feb 2017


City Residence is in the heart of the new regeneration zone of Liverpool Central North. Located less than 3 minutes from the commercial & business centres in Liverpool and minutes to Sandhills train station which links to the underground and bus routes.

The report outlines the work that has been carried out since November and has proved to be progressing speedily.

Construction is within schedule and the developer has not advised of any changes to the completion date.

 

City Residence Drone Footage – February 2018

 

 

City Residence – Construction Updates

City Residence Construction Update – September 2018

City Residence Construction Update – August 2018

City Residence Construction Update – July 2018

City Residence Construction Update – June 2018

City Residence Construction Update – May 2018

City Residence Construction Update – April 2018

City Residence Construction Update – November 2017

City Residence Construction Update – October 2017

City Residence Construction Update – September 2017

City Residence Construction Update – July 2017

 

City Residence – Construction Update May 2017

All of the four bed houses on Stanley Road are now to first lift brickwork, with first lift scaffold erected on all of these houses. Joiners are onsite and installing joists to hold the floor on the first floor level on half of the houses, with the other half to follow shortly.

The three bed houses on Lemon Street side of the site are now also to first lift brickwork, with first lift scaffold erected on all of these houses and joiners scheduled to install joists next week.

The three bed houses on the Great Mersey Street side of the site have slabs in place, with brickwork to damp course level scheduled to commence next week.


City Residence – Construction Update April 2017

All civil engineering infrastructure is now completely installed, including drainage, ancillary services and the new road has had the first layer of tarmac.
​ ​
All houses have had a 'block and beam' foundation installed and brickwork to damp course level. The next stage will be for brickwork to be constructed and the structure of the houses will become defined shortly.


City Residence – Construction Update March 2017

The main areas of progress in the build of City Residence in the last month includes all plots being up to slab level, and main drainage for waste and surface water is also now also installed.

Infrastructure works are currently being carried out to the new road that will link the site to Lemon Street and Great Mersey Street, with a view to base coating the road in the very near future.

The development on site is running according to plan, and on target for completion as expected in Q4 of 2017.


City Residence – Construction Update Feb 2017

Following the plot clearance in November, the construction team have been working hard (including on Boxing Day) to dig down to foundation levels of all houses.

Since the short Christmas & New Year break, we are delighted with the speed of progress, and all houses have had piling completed, foundations installed and some houses have even got the first course of brickwork now in place.

Therefore, the build is currently running to schedule.Regular updates will be sent out at each stage of construction from foundations through to completion of the building. If you need any further information in the mean time, please feel free to call us at the following offices:

Published in Capital